When scheduling the audit work to be performed on an engagement, the auditors should consider confirming accounts receivable balances at an interim date if:

A. Subsequent collections are to be reviewed.

B. Internal control over receivables is good.

C. Negative confirmations are to be used.

D. There is a simultaneous examination of cash and accounts receivable.

+1
Answers (1)
  1. 9 February, 20:51
    0
    The correct answer is letter "B": Internal control over receivables is good.

    Explanation:

    Only in the case the internal control of an organization is well-established enough so those account receivables (AR) are paid according to the terms agreed between the organization and its debtors, auditors could consider the balance of the account receivables at a provisional date.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “When scheduling the audit work to be performed on an engagement, the auditors should consider confirming accounts receivable balances at an ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.