Sheria has to evaluate whether she has enough in-house staff working on her project. What steps should she go through to compute this?

A. She should divide up the tasks according to which members are the most productive.

B. She should ask each team member to commit to 20 hours per week and adjust the number of tasks so that they can be completed in that time frame.

C. She should compute number of hours each in-house task on the schedule will take and compare that to the total number of work hours available from her team members.

D. She should compute the number of hours from the schedule starting date to the ending date and divide that by the number of team members.

+1
Answers (1)
  1. 7 April, 20:45
    0
    The answer is going to be A
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Sheria has to evaluate whether she has enough in-house staff working on her project. What steps should she go through to compute this? A. ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.