Ask Question
9 September, 19:35

The project manager building a new underwater dolphin exhibit at Chicago's Shedd Aquarium is reviewing the chronological sequence of activities that must be completed on the project and the estimated time of completion of each activity. He is employing the

A. Gantt chart.

B. total quality management process.

C. PERT technique.

D. lean manufacturing process.

+2
Answers (1)
  1. 9 September, 19:45
    0
    Answer: C. PERT technique

    Explanation:

    Project Evaluation and Review Technique is a technique used by project managers to control an ongoing project.

    It is also used to analyse and followup project activities in order to meet up with the deadline for the project.

    PERT is mainly used to analyse and control a project. Its main objective is to reduce project cost as well as manage the allotted time for the completion of the project.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “The project manager building a new underwater dolphin exhibit at Chicago's Shedd Aquarium is reviewing the chronological sequence of ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers