The project manager building a new underwater dolphin exhibit at Chicago's Shedd Aquarium is reviewing the chronological sequence of activities that must be completed on the project and the estimated time of completion of each activity. He is employing the
A. Gantt chart.
B. total quality management process.
C. PERT technique.
D. lean manufacturing process.
+2
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “The project manager building a new underwater dolphin exhibit at Chicago's Shedd Aquarium is reviewing the chronological sequence of ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.