Taussig Snow Removal's cost formula for its vehicle operating cost is $1,880 per month plus $394 per snow-day. For the month of February, the company planned for the activity of 13 snow-days, but the actual level of activity was 14 snow-days. The actual vehicle operating cost for the month was $7,250. The activity variance for vehicle operating cost in February would be closest to:

a. $394 F

b. $248 U

c. $394 U

d. $248 F

+3
Answers (1)
  1. 10 August, 15:45
    0
    The activity variance for vehicle operating cost in February would be closest to $394 U.

    Explanation:

    To calcuate the activity variance for vehicle operating cost in February we have to use calculate first the flexible budget and the planning budget.

    Flexible budget = $1,880 + ($394 * 14) = $7,396

    Planning budget = $1,880 + ($394 * 13) = $7,002

    Hence, the Activity variance=$394

    Therefore, as the flexible budget is greater than the planning budget, the variance is unfavorable (U).

    The activity variance for vehicle operating cost in February would be closest to $394 U.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Taussig Snow Removal's cost formula for its vehicle operating cost is $1,880 per month plus $394 per snow-day. For the month of February, ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.