In activity-based costing, the activity rate for an activity cost pool is computed by dividing the total overhead cost in the activity cost pool by:

a. the direct labor-hours required by the product.

b. the machine-hours required by the product.

c. the total activity for the activity cost pool.

d. the total direct labor-hours for the activity cost pool

+3
Answers (1)
  1. 16 March, 18:25
    0
    c. the total activity for the activity cost pool.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “In activity-based costing, the activity rate for an activity cost pool is computed by dividing the total overhead cost in the activity cost ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.