Suppose task B follows task A. The likelihood that a problem will occur with task A is 0.5, and the time to correct the problem would be 2 months. The likelihood that a problem will occur with task B is 0.2, and the time to correct the problem would be 3 months. The risk consequence of both activities is

A - 3.5 months

B - 5.7 months

C - 1.6 months

D - 2.1 months

+3
Answers (1)
  1. 30 November, 12:29
    0
    B

    Explanation:

    5.7
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Suppose task B follows task A. The likelihood that a problem will occur with task A is 0.5, and the time to correct the problem would be 2 ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.