If, for this machine, design capacity is 50 cords per day, effective capacity is 40 cords per day, and actual output is expected to be 30 cords per day, what would be its utilization?

+3
Answers (1)
  1. 17 July, 22:53
    0
    60%

    Explanation:

    Data provided as per the question is below

    Design capacity = 50 cords per day

    Effective capacity = 40 cords per day

    Actual output = 30 cords per day

    The computation of utilization is shown below:-

    Utilization = Actual output : Design capacity

    = 30 : 50

    = 0.6

    or 60%

    Therefore for computing the utilization we simply divide design capacity by actual output.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “If, for this machine, design capacity is 50 cords per day, effective capacity is 40 cords per day, and actual output is expected to be 30 ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.