In January the company produced 4,400 units using 10,180 pounds of the direct material and 2,160 direct labor-hours. During the month, the company purchased 10,750 pounds of the direct material at a cost of $76,630. The actual direct labor cost was $38,250 and the actual variable overhead cost was $11,951. The company applies variable overhead on the basis of direct labor-hours. The direct materials purchases variance is computed when the materials are purchased. The materials price variance for January is:

+2
Answers (1)
  1. 2 August, 20:49
    0
    The question is in complete (the tutor added $8 as standard material price)

    In January the company produced 4,400 units using 10,180 pounds of the direct material and 2,160 direct labor-hours. During the month, the company purchased 10,750 pounds of the direct material at a cost of $76,630. The actual direct labor cost was $38,250 and the actual variable overhead cost was $11,951. The company applies variable overhead on the basis of direct labor-hours. The direct materials purchases variance is computed when the materials are purchased. The materials price variance for January is:

    Assuming a standard material price of $8 per pound

    (Note this was added by the tutor)

    Answer:

    Price variance $9,370 Favorable

    Explanation:

    Material price variance

    A material price variance occurs where materials are purchased at a price either lower or higher than the standard price. A favorable variance is recorded where the actual total cost of materials is lower that the standard cost. While an adverse variance implies the opposite

    $

    10750 pounds should have cost (10,750 * $8) 86,000

    but did cost (actual cost 76,630

    Price variance 9,370 Favorable
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “In January the company produced 4,400 units using 10,180 pounds of the direct material and 2,160 direct labor-hours. During the month, the ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.