Playtime Industries manufactures custom-designed playground equipment for schools and city parks. Playtime expected to incur $ 586 comma 600 of manufacturing overhead cost, 41 comma 900 of direct labor hours, and $ 1 comma 592 comma 200 of direct labor cost during the year (the cost of direct labor is $38 per hour). The company allocates manufacturing overhead on the basis of direct labor hours. During May , Playtime completed Job 304. The job used 190 direct labor hours and required $ 14 comma 800 of direct materials. The City of Jonestown has contracted to purchase the playground equipment at a price of 28 % over manufacturing cost. Requirements:1. Calculate the manufacturing cost of Job 304.2. How much will the City of Jonestown pay for this playground equipment?

+3
Answers (1)
  1. 18 November, 05:28
    0
    Total cost = $24,680

    Selling price = $31,590.4

    Explanation:

    Giving the following information:

    Estimated overhead costs = $586,600

    Estimated direct labor hours = 41,900

    Estimated direct labor costs = $1,592,200 ( $38 per hour)

    Job 304:

    The job used 190 direct labor hours

    $14,800 of direct materials.

    The City of Jonestown has contracted to purchase the playground equipment for 28% over manufacturing cost.

    First, we need to calculate the predetermined overhead rate:

    Predetermined manufacturing overhead rate = total estimated overhead costs for the period / total amount of allocation base

    Predetermined manufacturing overhead rate = 586,600/41,900

    Predetermined manufacturing overhead rate = $14 per direct labor hour

    Now, total cost of Job 304:

    Total cost = direct material + direct labor + allocated overhead

    Total cost = 14,800 + (38*190) + (14*190)

    Total cost = $24,680

    Finally, the selling price:

    Selling price = 24,680*1.28 = $31,590.4
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Playtime Industries manufactures custom-designed playground equipment for schools and city parks. Playtime expected to incur $ 586 comma ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.