It is week 1 and there are currently 20 As in stock. We need 300 As at the start of week 5. If there are scheduled receipts planned for week 3 and week 4 of 120 As each and A has a lead time of 1 week, when and how large of an order should be placed to meet the requirement of 300 As?

+5
Answers (1)
  1. 29 July, 07:24
    0
    40 units at the start of week 4

    Explanation:

    Week Quantity Accumulated Quantity

    1 20 20

    2 0 20

    3 120 140

    4 120 260 - --> Order by 40 units *

    5 40 * 300

    * 40 units, received in week 5, from order placed 1 week before (week 4)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “It is week 1 and there are currently 20 As in stock. We need 300 As at the start of week 5. If there are scheduled receipts planned for ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.