When Job 117 was completed, direct materials to ob 117 was completed, direct materials totaled $4.400: direct labor, $5,600, and factory overhead, $2,400. A total of 1.000 units were produced at a per-unit cost of

a. $12,400

b. $1,240

c. S124

d. $12.40

+2
Answers (2)
  1. 29 August, 00:52
    0
    d. $ 12.40

    Explanation:

    Computation of Per Unit Cost

    Direct materials $ 4,400

    Direct labor $ 5,600

    Factory Overhead $ 2,400

    Total manufacturing costs $ 12,400

    Units produced 1000 units

    Cost per unit = Total manufacturing costs / No of Units produced

    Cost per unit = $ 12,400 / 1000 = $ 12.40 per unit
  2. 29 August, 00:56
    0
    The correct answer is D.

    Explanation:

    Giving the following information:

    direct materials totaled $4,400

    direct labor, $5,600

    factory overhead, $2,400.

    A total of 1,000 units were produced

    First, we need to calculate the total cost:

    Total cost = direct material + direct labor + allocated overhead

    TC = 4,400 + 5,600 + 2,400 = $12,400

    Now, we can calculate the unitary cost:

    Unitary cost = 12,400/1,000 = $12.4
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “When Job 117 was completed, direct materials to ob 117 was completed, direct materials totaled $4.400: direct labor, $5,600, and factory ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.