The project team toiled long into the night to develop consequence of failure scores and probability of failure scores as indicated below. What is the overall risk factor for the project?

A) Less than or equal to 0.7

B) Greater than 0.7 but less than or equal to 0.8

C) Greater than 0.8 but less than or equal to 0.9

D) Greater than 0.9

Maturity 0.7 Cost 0.4

Complexity 0.6 Schedule 0.6

Dependency 0.8 Reliability 0.8

Performance 0.9

+5
Answers (1)
  1. 18 December, 19:12
    0
    C

    Explanation:

    Greater than 0.8 but less than or equal to 0.9
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “The project team toiled long into the night to develop consequence of failure scores and probability of failure scores as indicated below. ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.