The actual cost of direct labor per hour is $14.75. Two and one half standard direct labor hours are allowed per unit of finished goods. During the current period, 3400 units were produced using 8300 direct labor hours. The direct labor efficiency variance is $3100 favorable. Calculate the standard direct labor rate per hour.
+5
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “The actual cost of direct labor per hour is $14.75. Two and one half standard direct labor hours are allowed per unit of finished goods. ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.