An X-bar R chart was prepared for an operation using twenty samples with 5 pieces in each sample. X-bar-bar was found to be 33.6and R=bar was 6.2. During production a sample of 5 was taken and the pieces measured 36, 43, 37, 25, and 38. At the time this sample was taken: Select the correct answer:
a. Both the average and range were within control limits.
b. Neither the average nor range were within control limits.
Find an answer to your question 👍 “An X-bar R chart was prepared for an operation using twenty samples with 5 pieces in each sample. X-bar-bar was found to be 33.6and R=bar ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.