Johnson Construction Company uses cost-plus pricing to determine costs and place bids on local jobs. The manager needs to compute the cost-plus price to place a bid on a custom room addition job. The estimated cost associated with the new room addition is $500,000. The markup on the project cost is 35%. What is the cost-plus price required to bid on the new custom room addition job?

+2
Answers (1)
  1. 3 February, 06:35
    0
    What is the cost-plus price required to bid on the new custom room addition job?

    $675000

    Explanation:

    Cost plus pricing=break even price*profit marginal goal

    Cost plus pricing=500000*1,35

    Cost Plus pricing=675000
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Johnson Construction Company uses cost-plus pricing to determine costs and place bids on local jobs. The manager needs to compute the ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers