Using PERT, Adam Munson was able to determine that the expected project completion time for the construction of a pleasure yacht is 21 months, and the project variance is 4.

a) What is the probability that the project will be completed in 17 months?

b) What is the probability that the project will be completed in 20 months?

c) What is the probability that the project will be completed in 23 months?

d) What is the probability that the project will be completed in 25 months?

e) What is the due date that yields a 95% chance of completion?

+5
Answers (1)
  1. 1 August, 06:43
    0
    Calculations are below

    Explanation:

    mean = 21

    s. d = sqrt (4) = 2

    a.) P (X<17) = P (Z< (17-21) / 2) = P (Z<-2) = 1 - 0.9772 = 0.0228

    b.) P (X<20) = P (Z< (20-21) / 2) = P (Z<-0.5) = 1 - 0.6915 = 0.3085

    c.) P (X<23) = P (Z< (23-21) / 2) = P (Z<1) = 0.8413

    d.) P (X<25) = P (Z< (25-21) / 2) = P (Z<2) = 0.9772

    e.) P (X
    z = 1.645

    (x - 21) / 2 = 1.645

    So x = 24.29

    SO 24.3 months
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Using PERT, Adam Munson was able to determine that the expected project completion time for the construction of a pleasure yacht is 21 ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.