A job was budgeted to require 3 hours of labor per unit at $8.00 per hour. the job consisted of 8,000 units and was completed in 22,000 hours at a total labor cost of $198,000. what is the total labor cost variance?
+2
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “A job was budgeted to require 3 hours of labor per unit at $8.00 per hour. the job consisted of 8,000 units and was completed in 22,000 ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.