A job was budgeted to require 3 hours of labor per unit at $8.00 per hour. the job consisted of 8,000 units and was completed in 22,000 hours at a total labor cost of $198,000. what is the total labor cost variance?

+2
Answers (1)
  1. 20 September, 03:58
    0
    The total labor cost of variance is the difference of the two presented costs. The actual cost of production is presented below,

    actual cost of production = $198,000

    The other cost can be calculated through the equation,

    cost of production = (3 hours/labor u) (($8/unit) (8,000) = $192,000

    Thus, the total labor cost variance is approximately $6,000.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “A job was budgeted to require 3 hours of labor per unit at $8.00 per hour. the job consisted of 8,000 units and was completed in 22,000 ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.