Addison Co. budgets production of 2,750 units during the second quarter. Other information is as follows: Direct labor Each finished unit requires 3 direct labor hours, at a cost of $7 per hour. Variable overhead Applied at the rate of $9 per direct labor hour. Fixed overhead Budgeted at $540,000 per quarter. 1. Prepare a direct labor budget. 2. Prepare a factory overhead budget.

+1
Answers (1)
  1. 11 May, 23:59
    0
    Direct Labor Hours Budget 8250

    Direct Labor Costs Budget $ 57750

    Factory Overhead Budget $ 614250

    Explanation:

    We multiply the direct labor hours per unit to the number of units to get the total direct labor hours which are again multiplied with the direct labor cost per hour to get the total direct labor costs.

    Addison Co.

    Direct Labor Budget

    Quarter II

    Production units 2750

    Direct Labor per unit 3

    Direct Labor Hours 8250

    Direct Labor Cost / Hr $7

    Direct Labor Costs $ 57750

    We multiply the direct labor costs with variable overhead per hour to get the variable costs which are added to the fixed costs per quarter to get the total factory overhead budget.

    Addison Co.

    Factory Overhead Budget

    Quarter II

    Direct Labor Hours 8250

    Variable OH / Hr $ 9

    Variable Overheads $ 74250

    +Fixed Overheads $ 540,000

    Factory Overhead Budget $ 614250
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Addison Co. budgets production of 2,750 units during the second quarter. Other information is as follows: Direct labor Each finished unit ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.