The predetermined overhead rate for Weed-B-Gone is $8, comprised of a variable overhead rate of $5 and a fixed rate of $3. The amount of budgeted overhead costs at normal capacity of $240,000 was divided by normal capacity of 30,000 direct labor hours, to arrive at the predetermined overhead rate of $8. Actual overhead for June was $15,800 variable and $9,100 fixed, and standard hours allowed for the product produced in June was 3,000 hours. The total overhead variance is:

A. $900 U.

B. $900 F.

C. $4,900 F.

D. $4,900 U.

+2
Answers (1)
  1. 23 February, 05:01
    0
    The answer is $A. $900 U.

    Explanation:

    We have the: Total overhead variance = Overhead applied - Actual overhead in which:

    + Overhead applied = Standard hours x Overhead application rate = 3,000 x 8 = $24,000;

    + Actual overhead = Variable overhead + fixed overhead = 15,800 + 9,100 = $24,900

    => Total overhead variance = Overhead applied - Actual overhead = 24,000 - 24,900 = 900 Unfavorable as the actual overhead is bigger than the overhead applied (planned cost is lower than actual cost incurred).

    So, the answer is A.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “The predetermined overhead rate for Weed-B-Gone is $8, comprised of a variable overhead rate of $5 and a fixed rate of $3. The amount of ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.