Hang Ten Company manufactures surf boards and uses an activityminusbased costing system to allocate all manufacturing conversion costs. Each surf board consists of 30 separate parts totaling $ 155 in direct materials, and requires 3 hours of machine time to produce. The company incurs no direct labor costs. Additional information follows: Activity Allocation Base Cost Allocation Rate Materials handling Number of parts $ 3.75 per part Machining Machine hours $ 2.00 per machine hour Assembling Number of parts $ 1.50 per part Packaging Number of finished units $ 2.75 per finished unit What is the total manufacturing cost per surf board?

+5
Answers (1)
  1. 13 February, 21:15
    0
    Total = $ 321.25

    Explanation:

    Giving the following information:

    Each surfboard consists of 30 separate parts totaling $ 155 direct materials and requires 3 hours of machine time to produce.

    Materials handling: Number of parts $ 3.75 per part

    Machining: Machine hours $ 2.00 per machine hour

    Assembling: Number of parts $ 1.50 per part

    Packaging: Number of finished units $ 2.75 per finished unit

    Total manufacturing cost:

    Direct materials = 155

    Materials handling=$ 3.75 * 30 = $112.5

    Machining: $ 2.00*3 = 6

    Assembling: $ 1.50*30 = 45

    Packaging: $ 2.75

    Total = $ 321.25
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Hang Ten Company manufactures surf boards and uses an activityminusbased costing system to allocate all manufacturing conversion costs. ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.