Firecracker Company has developed the following standards for one of its products. Direct materials: 15 pounds * $16 per pound Direct labor: 4 hours * $24 per hour Variable manufacturing overhead: 4 hours * $14 per hour The following activity occurred during the month of October: Materials purchased: 10,000 pounds costing $170,000 Materials used: 7,200 pounds Units produced: 500 units Direct labor: 2,300 hours at $23.60/hour Actual variable manufacturing overhead: $30,000 The company records materials price variances at the time of purchase. The direct materials price variance is

+2
Answers (1)
  1. 20 May, 13:36
    0
    (-$10,000) Unfavorable

    Explanation:

    Direct materials:

    Quantity = 15 pounds

    Standard price = $16 per pound

    Actual price = Purchase Price : Purchase quantity

    = 170,000 : 10,000

    = 17

    Material price variance:

    = Actual purchase quantity * (Standard price - Actual price)

    = 10,000 * ($16 - $17)

    = 10,000 * (-$1)

    = (-$10,000) Unfavorable
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Firecracker Company has developed the following standards for one of its products. Direct materials: 15 pounds * $16 per pound Direct ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.