Petrus Framing's cost formula for its supplies cost is $1,730 per month plus $11 per frame. For the month of March, the company planned for activity of 613 frames, but the actual level of activity was 618 frames. The actual supplies cost for the month was $8,670. The activity variance for supplies cost in March would be closest to: Multiple Choice $55 F $55 U $197 U $197 F
+2
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Petrus Framing's cost formula for its supplies cost is $1,730 per month plus $11 per frame. For the month of March, the company planned for ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.