Acheson Corporation, which applies manufacturing overhead on the basis of machine-hours, has provided the following data for its most recent year of operations. Estimated manufacturing overhead $ 157,300 Estimated machine-hours 4,550 Actual manufacturing overhead $ 156,500 Actual machine-hours 4,680 The estimates of the manufacturing overhead and of machine-hours were made at the beginning of the year for the purpose of computing the company's predetermined overhead rate for the year. The predetermined overhead rate is closest to:

+1
Answers (1)
  1. 24 July, 03:45
    0
    Estimated manufacturing overhead rate = $34.57 per machine hour.

    Explanation:

    Giving the following information:

    Acheson Corporation applies manufacturing overhead based on machine-hours.

    Estimated manufacturing overhead $ 157,300

    Estimated machine-hours 4,550

    To calculate the estimated manufacturing overhead rate we need to use the following formula:

    Estimated manufacturing overhead rate = total estimated overhead costs for the period / total amount of allocation base

    Estimated manufacturing overhead rate = 157,300 / 4,550 = $34.57 per machine hour.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Acheson Corporation, which applies manufacturing overhead on the basis of machine-hours, has provided the following data for its most ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.