A company is designing a product layout for a new product. It plans to use this production line eight hours a day in order to meet projected demand of 480 units per day. The tasks necessary to produce this product:

Task Time (sec) Immediate Predecessor

u 30 none

v 30 u

w 6 u

x 12 w

y 54 x

z 30 v, y

If the company desires that output rate equal demand, what is the desired cycle time (in seconds) ?

(A) 162

(B) 72

(C) 54

(D) 12

(E) 60

+1
Answers (1)
  1. 17 August, 03:42
    0
    desired cycle time: 60 seconds

    Explanation:

    The desired cycle time should match production with demand

    If there is a demand per day of 480 units then the cycle time should be:

    8 hours x 60 minute x 60 seconds = 28,800 second

    we divide this by the 480 units of demand:

    28,800 second / 480 units = 60‬

    The company needs to complete a unit in a 60 second time period.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “A company is designing a product layout for a new product. It plans to use this production line eight hours a day in order to meet ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.