A company is designing a product layout for a new product. It plans to use this production line eight hours a day in order to meet projected demand of 480 units per day. The tasks necessary to produce this product:
Task Time (sec) Immediate Predecessor
u 30 none
v 30 u
w 6 u
x 12 w
y 54 x
z 30 v, y
If the company desires that output rate equal demand, what is the desired cycle time (in seconds) ?
(A) 162
(B) 72
(C) 54
(D) 12
(E) 60
+1
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “A company is designing a product layout for a new product. It plans to use this production line eight hours a day in order to meet ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.