Lawrence Company applies manufacturing overhead to jobs based on machine hours used.

Overhead costs are estimated to be $300,000.

Estimated machine hours are 125,000 hours, and estimated direct labor hours are 50,000 hours.

During the year, actual overhead costs totaled $322,0000 and it incurred 130,000 machine hours and 46,000 direct labor hours.

What is the amount of over or under-allocated overhead?

+3
Answers (1)
  1. 24 June, 15:37
    0
    Under/over applied overhead = $10,000 underallocated

    Explanation:

    Giving the following information:

    Overhead costs are estimated to be $300,000.

    The estimated machine hours are 125,000 hours.

    During the year, actual overhead costs totaled $322,0000 and it incurred 130,000 machine hours.

    First, we need to calculate the estimated manufacturing overhead rate:

    Estimated manufacturing overhead rate = total estimated overhead costs for the period / total amount of allocation base

    Estimated manufacturing overhead rate = 300,000/125,000 = $2.4 per machine hour

    Now, we can allocate overhead

    Allocated MOH = Estimated manufacturing overhead rate * Actual amount of allocation base

    Allocated MOH = 2.4*130,000 = $312,000

    Finally, we determine the under/over allocation:

    Under/over applied overhead = real overhead - allocated overhead

    Under/over applied overhead = 322,000 - 312,000 = $10,000 underallocated
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Lawrence Company applies manufacturing overhead to jobs based on machine hours used. Overhead costs are estimated to be $300,000. Estimated ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.