The district magistrate of a city has decided to reconstruct the most frequented street of the city. He plans to block the street for the duration of the work, which will cause considerable inconvenience to the people of the city. The project has three parallel paths defined as the following:

Path A-B-C-H will take 16 days.

Path A-D-E-H will take 22 days.

Path A-F-G-H will take 30 days.

In the given scenario, which of the following statements is true?

a.

The expected duration of the project is 68 days.

b.

Activities B, D, and F have an earliest starting time of 0.

c.

Path A-D-E-H has the largest slack time.

d.

Path A-F-G-H is the critical path.

+1
Answers (1)
  1. 8 January, 03:17
    0
    The correct answer is B
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “The district magistrate of a city has decided to reconstruct the most frequented street of the city. He plans to block the street for the ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.