When Job 117 was completed, direct materials totaled $4,400; direct labor, $5,600; and factory overhead, $2,400. A total of 1,000 units were produced at a per-unit cost of a.$12,400 b.$1,240 c.$124 d.$12.40

+2
Answers (1)
  1. 2 November, 02:02
    0
    d.$12.40

    Explanation:

    The computation of the per unit cost is shown below:

    = Total cost : Number of units produced

    where,

    Total cost = Direct material cost + Direct labor cost + Factory overhead cost

    = $4,400 + $5,600 + $2,400

    = $12,400

    And, the units produced = 1,000 units

    So per unit cost equal to

    = $12,400 : 1,000 units

    = $12.40
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “When Job 117 was completed, direct materials totaled $4,400; direct labor, $5,600; and factory overhead, $2,400. A total of 1,000 units ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.