Given the following cost and activity observations for Bounty Company's utilities, use the high-low method to calculate Bounty' variable utilities costs per machine hour. Round your answer to the nearest cent. Cost Machine Hours March $3,100 15,000 April 2,700 10,000 May 2,900 12,000 June 3,600 18,000 a. $0.67 b. $10.00 c. $0.63 d. $0.11

+1
Answers (1)
  1. 11 July, 11:02
    0
    The option d is correct.

    Explanation:

    The high low method shows the difference between the high and low cost of a particular thing. In the given question, the high cost is $3,600 and the low cost is $2,700 whereas the high machine hour is 18000 and low machine hour is 10,000.

    Now, the formula for high low method is calculated. It is shown below:

    High low method = (High cost - Low cost) : (High machine hours - Low machine hours)

    = ($3,600 - $2,700) : (18000 - 10,000)

    = 900 : 8000

    = 0.11

    Thus, the option d is correct.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Given the following cost and activity observations for Bounty Company's utilities, use the high-low method to calculate Bounty' variable ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.