One employee is in charge of the following activities at a drive-through of a bank: Activity Activity Time per Customer Greet customer 2 seconds Take order 3 seconds Process order 2 minutes Print receipt 10 seconds What is the processing time (in seconds) of the drive-through process at the bank?
+3
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “One employee is in charge of the following activities at a drive-through of a bank: Activity Activity Time per Customer Greet customer 2 ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.