Which of the following cognitive biases occurs when decision makers commit even more resources if they receive feedback that the project is failing?

Options:

O Prior hypothesis bias

O Escalating commitment

O Illusion of control

O Reasoning by analogy

+5
Answers (1)
  1. 29 October, 07:24
    0
    The correct answer is letter "B": Escalating commitment.

    Explanation:

    Escalating commitment implies adding more resources to a project that is failing. The reason why more resources are added is that the individuals in charge of the project do not want to make it look inconsistent. Those resources are diverse and include capital, labor or raw materials.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Which of the following cognitive biases occurs when decision makers commit even more resources if they receive feedback that the project is ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers