Type the correct answer in the box. Spell all words correctly.

A movie studio committed to the production of two additional sequels after a successful franchise was launched. However, the story quality of the two sequels was poor and critics gave them low ratings. As a result, attendance figures were very low. What risk did the movie studio suffer from?

___risk negatively impacted the studio's business.

+2
Answers (1)
  1. 4 October, 05:17
    0
    Quality risk

    Explanation:

    Quality risk is a risk that emerges out of failure to meet quality goals for a particular product, service or business practice.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Type the correct answer in the box. Spell all words correctly. A movie studio committed to the production of two additional sequels after a ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.