Benton Lamps applies overhead using direct labor hours. Budgeted total overhead cost was $472,000 and estimated direct labor hours were 118,000 for the first quarter. The standard direct labor quantity is 4 hours per lamp, and the company produced 9,800 lamps in January. This required 39,500 direct labor hours. What amount should be used for overhead applied in the total overhead variance calculation?

+5
Answers (1)
  1. 30 January, 05:42
    0
    Allocated MOH = $158,000

    Explanation:

    Giving the following information:

    The standard direct labor quantity is 4 hours per lamp, and the company produced 9,800 lamps in January. This required 39,500 direct labor hours.

    Allocated MOH = Estimated manufacturing overhead rate * Actual amount of allocation base

    Allocated MOH = 4*39,500 = $158,000
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Benton Lamps applies overhead using direct labor hours. Budgeted total overhead cost was $472,000 and estimated direct labor hours were ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.