Ask Question
18 April, 23:25

The short-term scheduling activity called "loading": Select one:

a. assigns workers to jobs.

b. assigns jobs to work centers

c. assigns workers to machines.

d. assigns dates to specific jobs or operations steps.

e. specifies the order in which jobs should be done at each center.

+2
Answers (1)
  1. 18 April, 23:43
    0
    b. assigns jobs to work centers

    Explanation:

    Initially an aggregate plan is prepared and then there is a master plan, accordingly with that master plan divided into smaller sections some short term schedules are prepared.

    Under the short term scheduling the term loading is done which refers to assignment of jobs to work centers.

    This provides for the segregation of duties and work in between different work centers as in which work center will perform which job.

    The company jointly performs all activities in order to meet the aggregate plan, by performing duties of each work center properly the goal can be achieved.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “The short-term scheduling activity called "loading": Select one: a. assigns workers to jobs. b. assigns jobs to work centers c. assigns ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers