A writer estimates it will take three months to generate spiffy documents to accompany a seminal work in operations management. He grossly underestimates the time required and misses his deadline by two months. This estimate was: A) Objective and inaccurate. B) Objective and accurate. C) Subjective and accurate. D) Subjective and inaccurate.
+3
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “A writer estimates it will take three months to generate spiffy documents to accompany a seminal work in operations management. He grossly ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.