Ask Question
20 September, 16:37

What is the multifactor productivity for Space Z Inc. using the following data?

10,000 Units Produced

Sold for $10/unit

500 labor hours

Labor rate: $9/hr

Cost of raw material: $30,000

Overhead: $15,50

+5
Answers (1)
  1. 20 September, 16:41
    0
    multi factory productivity = 2.37

    Explanation:

    Giving the following information:

    10,000 Units Produced

    Sold for $10/unit

    500 labor hours

    Labor rate: $9/hr

    Cost of raw material: $30,000

    Overhead: $15,50

    To calculate the multi factory productivity, we need to use the following formula:

    multi factory productivity = output / (labor + material + overhead)

    multi factory productivity = (10,000*10) / (4,500 + 30,000 + 7,750)

    multi factory productivity = 2.37
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “What is the multifactor productivity for Space Z Inc. using the following data? 10,000 Units Produced Sold for $10/unit 500 labor hours ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers