Ask Question
23 September, 18:05

Cadavieco Detailing's cost formula for its materials and supplies is $1,990 per month plus $8 per vehicle. For the month of November, the company planned for activity of 92 vehicles, but the actual level of activity was 52 vehicles. The actual materials and supplies for the month was $2,440. The activity variance for materials and supplies in November would be closest to:a. $286 U

b. $320 U

c. $286 F

d. $320 F

+4
Answers (1)
  1. 23 September, 18:15
    0
    Answer: Option D - - $320 F

    Explanation:

    [ (P-O) : 6]^2, if properly calculated for the above question. The activity variance for materials and supplies in November would be closest to $320F. It should be noted that, The standard deviation for the project as a whole is the sum of all the activity variances, in order word, standard deviation is the square root of variance.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Cadavieco Detailing's cost formula for its materials and supplies is $1,990 per month plus $8 per vehicle. For the month of November, the ...” in 📗 Business if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers