Consider the steps in a bicycle-factory assembly line: Step 1: rate = 120 handlebars per hour Step 2: rate = 60 sets of wheels per hour Step 3: rate = 240 seats per hour What is the fastest rate at which the assembly line can produce complete bicycles?

+3
Answers (2)
  1. 27 March, 08:40
    0
    60 bicycles

    Explanation:

    The slowest step determines the overall rate of the process.
  2. 27 March, 08:51
    0
    Answer:60 and slowest determines overall

    Explanation:

    I took the warm up assignment
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Consider the steps in a bicycle-factory assembly line: Step 1: rate = 120 handlebars per hour Step 2: rate = 60 sets of wheels per hour ...” in 📗 Chemistry if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.