A project manager receives an email stating that a report will be turned in late. What impact will this have on the project?

A. Cost of the project will decrease

B. Resources will be eliminated

C. Scope of the work will be increased

D. Timeline of the project may change

+3
Answers (1)
  1. 31 July, 14:21
    0
    D. Timeline of the project may change

    Explanation:

    In a project, activities tend to have a dependency relationship on one another. Delay in one activity may result in project schedule slippage if it happens to be on the critical path. As a result, when a project manager receives a communication about one of the tasks getting delayed - namely, the report being late, it implies that the timeline of the project may possibly change.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “A project manager receives an email stating that a report will be turned in late. What impact will this have on the project? A. Cost of the ...” in 📗 Computers & Technology if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers