The most common type of logical dependency to determine the sequence of project activities is "finish-to-finish" (FF).

a. True

b. False

+3
Answers (1)
  1. 21 June, 04:36
    0
    Option B i. e., False is the correct option.

    Explanation:

    The following statement is incorrect because, It is the logical relationship not the logical dependency to recognize the series of the activity of the project details. So, that's why the following option is correct according to the given statement. the following relationship is also established between the specific schedule.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “The most common type of logical dependency to determine the sequence of project activities is "finish-to-finish" (FF). a. True b. False ...” in 📗 Computers & Technology if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.