Ask Question

The Material Requirements Plan (MRP) uses which of the following to calculate requirements?

= Bill of material, payroll schedule, and capacity plan

=Master production schedule and capacity plan

= Inventory data, production strategy, and supplier list

= Master production schedule, bill of material, and inventory data

+3
Answers (1)
  1. 18 February, 08:23
    0
    Master production schedule, bill of material, and inventory data

    Explanation:

    The Material Requirements Plan (MRP) is an analysis that lists the material/components needed in order to produce something.

    First, you need to take into account the material needed, then the inventory you currently have then plan the acquisition of the material for the production to continue.

    Answer A talks about payroll, that has nothing to do with the MRP.

    Answer B talks about capacity plan, that has nothing to do with the MRP.

    Answer C talks about suppliers list, that's related but not precisely part of the MRP.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “The Material Requirements Plan (MRP) uses which of the following to calculate requirements? = Bill of material, payroll schedule, and ...” in 📗 Computers & Technology if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers