Which logical relationship does the PDM usemost often?

Start to finish

Start to start

Finish to finish

Finish to start

+5
Answers (1)
  1. 17 June, 06:42
    0
    Finish to Start.

    Explanation:

    Finish to Start dependency also known as FS is most commonly used dependency type used between activities in PDM (Precedence Diagramming Method). For example : - in a software you cannot test a screen before it is developed, in construction you cannot paint a building before it is constructed. So we conclude that Finish to start is most commonly used.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Which logical relationship does the PDM usemost often? Start to finish Start to start Finish to finish Finish to start ...” in 📗 Computers & Technology if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.