A contractor is preparing a bid to install swimming pools at a new housing addition. The estimated time to build the first pool is 33 hours. The contractor estimates an 80 percent learning rate. Using POM for Windows or OM Explorer, how long do you estimate the time required to install the fifth pool?

+4
Answers (1)
  1. 4 January, 06:19
    0
    26.4 hour

    21.12 hours

    Explanation:

    To properly answer this question, we will multiply the estimated time to build the first pool in 33 hours by the percentage of of the contractors estimate.

    Thus, we have,

    33 x 0.80 = 26.4. This is assumed to be the estimated time to build the second pool.

    Now, moving forward to calculate the estimated time to install the fifth pool, we multiply the estimated time for the second pool by percentage of the contractors estimate.

    That is:

    26.4 X 0.80 = 21.12

    Hence, 21.12 is the assumed estimated time required to install the fifth pool.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “A contractor is preparing a bid to install swimming pools at a new housing addition. The estimated time to build the first pool is 33 ...” in 📗 Computers & Technology if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.