In a PERT network, non-critical activities that have little slack need to be monitored closely
a. because PERT treats all activities as equally important
b. because near-critical paths could become critical paths with small delays in these activities
c. because slack is undesirable and needs to be eliminated
d. because they are causing the entire project to be delayed e. because they have a high risk of not being completed
+3
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “In a PERT network, non-critical activities that have little slack need to be monitored closely a. because PERT treats all activities as ...” in 📗 Computers & Technology if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Home » Computers & Technology » In a PERT network, non-critical activities that have little slack need to be monitored closely a. because PERT treats all activities as equally important b.