4. What aspect of the initial database planning process would the formula (0 + Pt * 3 + p) / 5 be used in?

A. Time estimation

B. Budgeting

C. Workforce forecasting

D. Entity prediction

+1
Answers (1)
  1. 26 September, 18:44
    0
    Time estimation makes the most since in this scenario
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “4. What aspect of the initial database planning process would the formula (0 + Pt * 3 + p) / 5 be used in? A. Time estimation B. Budgeting ...” in 📗 Computers & Technology if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.