4. In the Hyatt Regency walkway case study, it is reported that Jack Gillum stamps the 42 shop drawings, including the revised Shop Drawing 30 and Erection Drawing E-3 denoting the revised hanger connection detail, with his engineering review seal, authorizing construction. When stamping these drawings, what is Jack Gillum accepting? A one-word response is sufficient.

+1
Answers (1)
  1. 14 June, 06:04
    0
    Responsibility

    Explanation:

    By stamping the drawings that he was looking over, Jack Gillum conveys the fact that he is accepting responsibility for this work. The purpose of Gillum's stamp is to explain that such work has been under engineering review, and that it has fulfilled all the requirements that he watches our for. By putting his stamp in this work, Gillum accepts responsibility in case an error or a discrepancy is found in the drawings.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “4. In the Hyatt Regency walkway case study, it is reported that Jack Gillum stamps the 42 shop drawings, including the revised Shop Drawing ...” in 📗 Engineering if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers