Estimate the quantity of soil to be excavated from the borrow pit

+3
Answers (1)
  1. 17 October, 23:20
    0
    Answer

    1056

    Explanation:

    for example

    A soil is to be excavated from a borrow pit which has a density of 1.75g/cc and water content of 12%. The G is 2.7 the soil is compacted to that water content of 18% and dry density of 1.65g/cc. for 1000 m3 of soil used in fill estimate

    Quantity of soil to be excavated from pit in m3