You are about to implement a system designed to improve productivity at the office. You look at all of your stakeholders and as you map them you realize that there are some department heads who do not want this system implemented.

What action should you take?

Show them how this is good for the overall company.

Ignore them. They are not your boss.

Keep them informed of the details as you move forward.

Learn why they don't want the system implemented.

+3
Answers (1)
  1. 11 November, 11:08
    0
    Answer: D. Learn why they don't want the system implemented.

    Explanation: You should try to understand why they oppose the project, perhaps they know something that you don't.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “You are about to implement a system designed to improve productivity at the office. You look at all of your stakeholders and as you map ...” in 📗 English if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers