The time required to do a job varies inversely as the number of people working. It takes 6 hr for 8 bricklayers to build a park wall. How long will it take 7 bricklayers to complete the job?

+3
Answers (2)
  1. 23 October, 09:09
    0
    It should be 5.25 hours

    Since it took 6 hours to build 8 bricklayers then it should take less time to build a 7 bricklayers

    First, set a proportion:

    Hours/bricklayers

    6/8 = x/7

    Then cross-multiply: 8x=42

    And finally, solve:

    x=5.25 hours
  2. 23 October, 09:14
    0
    6 6/7 hrs

    Step-by-step explanation:

    The general equation for inverse proportion is y = k/x, where k is the constant of proportionality. We need to determine the value of k from the given dа ta:

    y = k/x becomes 6 = k/8, so that k = 48.

    Then y = 48/x represents the length of time required for x bricklayers to build the wall.

    If there are 7 bricklayers, then x = 7, and y = 48/7

    It requires 7 bricklayers 48/7 hours (6 6/7 hours) to build the wall.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “The time required to do a job varies inversely as the number of people working. It takes 6 hr for 8 bricklayers to build a park wall. How ...” in 📗 Mathematics if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.