Roget Factory has budgeted factory overhead for the year at $4,958,800. It plans to produce 2,000,000 units of product. Budgeted direct labor hours are 322,000, and budgeted machine hours are 750,000. Using a single plantwide factory overhead rate based on direct labor hours, the factory overhead rate for the year is?

+1
Answers (1)
  1. 12 August, 15:18
    0
    Step-by-step explanation:

    Factory overhead could be defined as the total amount incurred in production excluding direct labor or material cost. They are expenses which cannot be traced directly to a product.

    Calculating factory overhead based on direct labor hours:

    Budgeted factory overhead = $4,958,800

    Budgeted direct labor hours = 322,000

    Factory overhead rate = (Budgeted factory overhead : Budgeted direct labor hours)

    Factory overhead rate = 4,958,800 : 322,000

    = $15.4
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “Roget Factory has budgeted factory overhead for the year at $4,958,800. It plans to produce 2,000,000 units of product. Budgeted direct ...” in 📗 Mathematics if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.