Ask Question
20 May, 06:45

12 men working 8 hours a day complete a piece of work in 10 days to complete a the same work in 8 days working 15 hours a days the number of men required is

+4
Answers (1)
  1. 20 May, 07:06
    0
    12 men : 8 hours : 10 days

    / / Find if every man works 1 hour

    12 x 8 men : 1 hour : 10 days

    96 men : 1 hour : 10 days

    //Find if every man works 15 hours

    96 : 15 men : 15 hours : 10 days

    6.4 men : 15 hours : 10 days

    //Find if every man works 1 day

    6.4 x 10 men : 15 hours : 1 day

    64 men : 15 hours : 1 day

    //Find if every man works 8 days

    64 : 8 men : 15 hours : 8 days

    8 men : 15 hours : 8 days

    Answer: 8 men is needed
Know the Answer?
Not Sure About the Answer?
Find an answer to your question 👍 “12 men working 8 hours a day complete a piece of work in 10 days to complete a the same work in 8 days working 15 hours a days the number ...” in 📗 Mathematics if the answers seem to be not correct or there’s no answer. Try a smart search to find answers to similar questions.
Search for Other Answers